Vertical rebar is set at 24" on center around the perimeter when the foundation is poured.
The forms are assembled and horizontal rebar is placed at 16" on center.   
Several courses are assembled to the proper wall height, and windows and doors are framed.
Bracing is installed to be sure walls are secure and plumb before the wall cavity is filled with concrete.
The walls are pumped full of concrete, truss straps are set, the bracing is removed and the exterior shell is rock solid! 
Wiring is installed quickly and easily using a hot knife to cut penetrations and channels in the foam.

Drywall is installed on the interior walls by fastening to the polypropylene webs embedded in the foam at 8" on center (twice is many fastening points as studs with traditional framing).  No furring strips or additional preparation is necessary for interior or exterior applications!

Brick, stucco, vinyl, hardi-board siding or other exterior applications are applied to the outside.
1
2
3
4
5
6
ICF CONSTRUCTION
The Installation Process
 
 
Building with insulated concrete forms is a simple process that is far less labor intensive than most traditional construction methods.  The lightweight forms assemble quickly and do not require additional steps for installing vapor barriers, furring strips or wall insulation.  An ICF wall is a complete system!


Check out photos of some of our ICF buildings by clicking here
Maximum Building Systems, Inc.  (850)728.6721   -  Crawfordville, FL